Backups are a mechanism. Disaster recovery is a promise: this client’s site will be back within this long, missing no more than this much data, and these named people will make it happen. Most agencies have the mechanism and have never written down the promise, so the promise gets made for the first time on the phone, during the outage, by whoever answers.
A disaster recovery plan closes that gap. For an agency it comes down to five things:
- Agreed targets per client — a recovery point objective (RPO) and a recovery time objective (RTO) that the client has accepted in writing, and that you have evidence you can meet.
- A recovery order for the whole portfolio, because the event that hurts is rarely one site; it is the hosting account, the DNS provider or the one person with the credentials.
- A written plan with roles and escalation, stored somewhere that survives the disaster it describes.
- Exercises: discussion-based tabletops for the decisions, and real recoveries for the mechanics. They test different things.
- A rule for what happens when a target is missed, in a drill or for real.
Scope, and where the backup mechanics live
This is for an agency running roughly 5 to 50 client WordPress or WooCommerce sites that wants to turn “we have backups” into recovery obligations it can defend.
It builds on the WordPress backup and restore checklist, and deliberately does not repeat it. That page covers the backup estate: inventory, what an archive actually contains, off-platform copies, retention, the per-site dependencies that break restores, and a single-site restore worksheet. If you have not done that work, do it first — none of the commitments below are honest without it.
This page covers what sits above it: business impact, the targets you agree with clients, the plan document, who does what and who gets told, and how you exercise the plan as a whole. Recoverability also appears as one control in the security checklist for agency client sites, and a planned move between hosts is covered by the migration runbook — a migration is a recovery you get to schedule, and much of the same preparation carries over.
Three terms, and a fourth number nobody writes down
NIST SP 800-34, the US federal contingency-planning guide, gives the widely used definitions. Paraphrased for a client site:
- Maximum tolerable downtime (MTD) — how long the client’s business process can be disrupted before it causes significant harm. This is a business fact about the client, not a technical setting. NIST’s glossary: “The amount of time mission/business process can be disrupted without causing significant harm to the organization’s mission.”
- Recovery time objective (RTO) — how long the site can stay in recovery before that harm arrives. NIST notes that because the RTO has to keep you inside the MTD, the RTO “must normally be shorter than the MTD” — the gap is the time the client needs after the site is back, to re-enter orders or re-send emails, for example.
- Recovery point objective (RPO) — the point in time to which data must be recovered. In practice: how much recent work the client can afford to lose. NIST is explicit that, unlike RTO, RPO is not part of the maximum tolerable downtime; it is about data loss, not duration.
The fourth number is the one that matters in an incident: demonstrated recovery time — how long a recovery actually took the last time your team did it, on a dated drill record. An RTO is a target. A demonstrated time is evidence. The gap between the two is what a DR plan exists to close, and an agency that commits to an RTO it has never demonstrated has made a promise it cannot back.
Step 1 — Business impact, client by client
Tiers are only useful if they are defined by consequence, not by site size or by how much the client pays. Ask each client four questions, and write the answers down in their words:
- What stops when the site is down? Sales, bookings, lead capture, support, a regulatory publication, or nothing urgent.
- What is lost if the last few hours of data disappear? Orders, form submissions, member sign-ups, content an editor wrote this morning.
- When does it hurt most? A launch, a seasonal peak, a weekly newsletter. An outage at the wrong time can cost more than a longer one at the right time.
- Does the site hold personal data? If so, an incident that loses or exposes it may carry legal duties as well as commercial ones (see Step 5).
Then sort each site into an impact tier. The definitions below are a judgement, not a standard; adjust the wording, but keep it about consequence:
| Tier | Defined by | What the DR plan owes it |
|---|---|---|
| High | Downtime or data loss directly stops revenue or a service people depend on; personal data at stake | Agreed RPO/RTO in the contract, a named runbook, first place in the recovery order, a real recovery exercise |
| Moderate | Downtime is damaging and visible but does not stop the client’s business | Agreed targets, a runbook, a recovery exercise at a lower cadence |
| Low | Downtime is an inconvenience; content changes rarely | Targets stated plainly, covered by the generic runbook and the tabletop |
The backup checklist has a tier table with indicative RPO and RTO ranges as a starting point. This page assumes you will replace those placeholders with numbers the client has actually agreed.
Step 2 — The RPO/RTO commitment worksheet
This is the first asset. Complete one per site, with the client, before anything goes into a contract. It forces the three numbers — what the client needs, what your setup implies, and what you have shown you can do — onto one page, so that any gap is a decision rather than a surprise.
RPO / RTO COMMITMENT WORKSHEET
Client / site ............... [ ]
Impact tier ................. [High / Moderate / Low]
Completed by ................ [name] With (client) [name, role]
Date ........................ [YYYY-MM-DD]
1. WHAT THE CLIENT NEEDS (their words, their numbers)
Maximum tolerable downtime (MTD) ......... [ ]
Time needed after recovery to catch up ... [ ]
Data loss they can tolerate .............. [ ]
Peak periods / blackout dates ............ [ ]
Personal data held? ...................... [Yes / No / Unknown]
2. WHAT THE TARGETS MUST THEREFORE BE
Required RTO (MTD minus catch-up time) ... [ ]
Required RPO ............................. [ ]
3. WHAT THE CURRENT SETUP IMPLIES
Database backup interval ................. [ ] -> worst-case RPO [ ]
File/media backup interval ............... [ ]
Off-platform copy exists? ................ [Yes / No]
Restore path relies on ................... [host feature / plugin / own pipeline]
Dependencies outside the backup .......... [DNS, email, licences, keys ...]
4. WHAT HAS BEEN DEMONSTRATED
Last restore drill record ................ [link to completed drill worksheet]
Drill date ............................... [YYYY-MM-DD]
Demonstrated recovery time ............... [ ] (blank = never tested)
Demonstrated data loss ................... [ ]
5. GAP AND DECISION
RTO gap (demonstrated minus required) .... [ ]
RPO gap (implied minus required) ......... [ ]
Decision ................................. [ ] Targets met on evidence
[ ] Change setup: [what, cost, owner, date]
[ ] Client accepts longer targets: [new RPO/RTO]
[ ] Plan of action to close gap: [ref]
6. AGREED COMMITMENT
Agreed RPO [ ] Agreed RTO [ ]
Recovery-order position in portfolio ..... [ ]
Applies from [YYYY-MM-DD] Review by [YYYY-MM-DD]
Agency sign-off [name] Client sign-off [name]
Section 4 links to the completed single-site restore drill worksheet rather than copying it. If that link has nowhere to point, the honest entry for demonstrated recovery time is “never tested”, and the honest decision is not “targets met”.
Three rules for using it:
- Commit to the demonstrated number, not the hoped-for one. If the client needs a shorter RTO than you have shown, the options are to change the setup and drill again, or to agree a longer target. Where the client’s requirement cannot be relaxed, NIST’s guidance for the same situation is to document the shortfall in a plan of action and milestones rather than leave it implicit.
- RPO is mostly a configuration question; RTO is mostly a people question. A nightly backup limits the achievable RPO to about a day no matter how good the team is. Recovery time depends on who is reachable, whether they can get the credentials, and whether they have done it before.
- A client who declines the cost of a shorter target has made a decision. Record it in section 5. It protects both of you when the outage comes.
Step 3 — Plan for the portfolio, not the site
Single-site recovery is covered elsewhere. The event a DR plan really exists for is the one that takes many sites at once, because that is when recovery times stack up and the order matters.
List your shared dependencies — the things that, if lost, take more than one client with them:
| Shared dependency | If it is lost | Question for the plan |
|---|---|---|
| Hosting account or server | Every site on it, possibly the host-held backups too | Where do we restore to, and is that account already open and paid for? |
| DNS provider / registrar account | Sites may be intact but unreachable | Who can log in, and where are the zone records kept outside the provider? |
| Backup storage account | Recovery is impossible, not just slow | Is access independent of the hosting account and of any one person? |
| Password manager / identity provider | Every other recovery step stalls | What is the break-glass route, and who holds it? |
| CDN / WAF in front of the sites | Traffic fails or bypasses filtering | Can DNS be repointed to origin safely, and who decides? |
| Transactional email service | Sites work; orders and resets do not arrive | Is the sending configuration documented outside the site? |
| The one person who knows | Everything slows to their availability | Who is the second person, and have they done it? |
Credential and break-glass access is covered in detail in WordPress access control for agencies, and the way your hosting architecture shapes this list is covered in three practical hosting architectures.
Then set a recovery order. NIST describes the last step of a business impact analysis as producing a recovery priority hierarchy from criticality, outage impact and tolerable downtime. For an agency that is a ranked list: which sites come back first if everything goes at once. Two checks against it:
- Capacity. How many recoveries can your team run at once? If the answer is one or two, the RTO of the fifth site on the list includes the time to recover the four ahead of it. Your per-site drill time does not capture this; only a portfolio exercise does.
- Consistency. If the order puts a low-tier site ahead of a high-tier one for a good reason — it shares infrastructure the others need, say — write the reason down.
Step 4 — The plan document
NIST SP 800-34 structures an IT contingency plan in three phases: activation and notification (detect, assess, decide to invoke the plan, tell the right people), recovery (restore in the agreed order), and reconstitution (validate the recovered system, return to normal, back it up, and document what happened). That structure scales down well. A plan an agency can actually use fits in a few pages:
| Section | Contents |
|---|---|
| Scope and owner | Which clients and sites it covers; who owns the plan and its review date |
| Activation criteria | When the plan is invoked rather than handled as routine support. NIST suggests criteria such as extent of damage, criticality, and an expected outage longer than the RTO |
| Roles and contacts | Named people, a deputy for each, out-of-hours contact routes, host and registrar support routes |
| Recovery order | The ranked list from Step 3, with each site’s agreed RPO and RTO |
| Scenario runbooks | One short runbook per scenario (below), each linking to the detailed procedures |
| Client communication | Who tells each client, what, and when — including the message when a target will be missed |
| Validation and close-down | Acceptance checks, a fresh backup of the recovered site, and who declares recovery complete |
| After-action and record of changes | Where incident and exercise reports go; a dated log of every change to the plan |
Scenario runbooks are where the plan becomes usable at 2am. Keep each to a page: the trigger, the first decision, the first three actions, who owns it, and a link to the procedure. The scenarios most agencies need:
- One site compromised (restore after taking a forensic copy — see the backup checklist’s failure modes)
- One site broken by a bad deployment or data corruption
- Hosting account suspended, locked or lost
- Host platform or region outage you cannot fix yourself
- DNS or registrar account lost or compromised
- Backup storage unavailable
- Key person unavailable during any of the above
Store the plan where the disaster cannot reach it. NIST recommends keeping a copy with the backup media and at the alternate site. For an agency that means a copy outside the hosting account, outside the company’s main document system if that sits behind the same identity provider, and reachable from a phone. A recovery plan that lives only on the server it describes is a common and avoidable failure.
Review it on a schedule and on change. NIST’s guidance is to review the plan at a set frequency and whenever something significant changes, with contact lists reviewed more often than the rest. Changing host, backup tool or DNS provider is a significant change.
Step 5 — Roles and escalation
Four roles cover most agency incidents. In a small agency one person may hold two, but never all four:
- Incident lead — decides that the plan is invoked, keeps the timeline, and makes the calls about order and trade-offs.
- Recovery operator — does the technical work from the runbook.
- Client communications owner — the only person who tells clients anything, so they hear one consistent account.
- Decision authority — the person who can approve spending, accept a missed target, or bring in outside help. Usually an agency principal.
Escalation should be tied to the targets, not to how worried people feel. A template to complete for each tier; the thresholds are yours to set, and are left blank deliberately:
| Trigger | Who is told | By when |
|---|---|---|
| Plan activation criteria met | Incident lead, recovery operator | [ ] |
| Client-facing impact confirmed | Client comms owner → client | [ ] |
| No working recovery path after [ ] % of RTO | Decision authority | [ ] |
| RTO or RPO will be missed | Client, before the target passes | [ ] |
| Suspected compromise or personal data involved | Decision authority; client as data controller | Without undue delay (see below) |
| External help needed (host, security responder) | Decision authority approves | [ ] |
Personal data changes the clock. If an incident involves personal data — including its accidental loss, or unavailability that significantly affects people, not only theft — data protection law may apply. Under UK GDPR, the ICO’s guidance is that a controller must report a notifiable breach “without undue delay, but not later than 72 hours after becoming aware of it”, and that a processor must inform the controller without undue delay. An agency maintaining a client’s site is often acting as a processor, which makes telling the client promptly your obligation and deciding whether to report theirs. The ICO also expects every breach to be documented, reported or not. This is a summary of UK guidance, not legal advice: other jurisdictions differ, and your contract should say who does what.
Step 6 — Testing: tabletop versus actual recovery
The two kinds of exercise are not substitutes. NIST, drawing on its exercise guide SP 800-84, describes a tabletop as discussion-based — a facilitator presents a scenario and participants talk through their roles and decisions — and not involving the deployment of equipment or other resources. A functional exercise has people perform their duties in a simulated environment, and can range from one aspect of the plan to a full-scale exercise covering all of it.
| Exercise | What it proves | What it cannot prove |
|---|---|---|
| Tabletop | Roles are understood; decisions and escalation work; the plan is findable; gaps in contacts and access | That any site can actually be restored, or how long it takes |
| Single-site restore drill | One site comes back from one backup, and how long that took | Portfolio capacity, order, communication under pressure |
| Portfolio recovery exercise | The plan works end to end for a realistic multi-site event, against agreed RTOs | Every possible scenario — it tests one |
NIST scales the exercise to the system’s impact level: a tabletop is sufficient for low-impact systems, moderate-impact systems call for a functional exercise that includes recovery from backup, and high-impact systems for a full-scale functional exercise. Mapped onto the tiers in Step 1 — a judgement, not a NIST requirement for agencies:
- Every year, at least: one tabletop of the whole plan, with every role holder present. NIST’s plan templates include an attestation that the plan will be tested at least annually, and its guidance is that people in recovery roles are trained at least annually.
- Per site, on the backup checklist’s cadence: single-site restore drills, rotating through the portfolio.
- For high-tier sites: a portfolio recovery exercise that recovers them in plan order into a separate environment, at a cadence you set and write into the plan.
- After any significant change — new host, new backup tooling, a new person in a recovery role — an exercise before the change is trusted.
Two free resources are worth knowing if you are writing your first tabletop. The UK NCSC’s Exercise in a Box is a free online service with tabletop and short micro exercises, usable by organisations without in-house exercise expertise, including small businesses. CISA publishes Tabletop Exercise Packages with template objectives, scenarios, discussion questions and an after-action report format. Neither is WordPress-specific; the scenario below is.
A tabletop scenario to run
Allow an hour. One facilitator reads the scenario and each inject in turn; the participants answer from the plan, not from memory. Record the answers in the blanks — the gaps are the output.
TABLETOP RECORD
Date [YYYY-MM-DD] Facilitator [name] Participants [names, roles]
Plan version under test [ref]
SCENARIO
It is a weekday, late afternoon. Monitoring alerts that several client
sites are returning errors. The hosting dashboard login fails for the
account that holds them.
INJECT 1 Who decides whether to invoke the plan, and against which criteria?
Answer [ ]
INJECT 2 The host's support route is slow to respond. Where are the
off-platform backups, who can reach them, and with what credentials?
Answer [ ]
INJECT 3 Where do we restore to? Is that account open and ready?
Answer [ ]
INJECT 4 Which site comes back first, second, third? Who says so?
Answer [ ]
INJECT 5 A high-tier client calls. Who speaks to them and what do they say?
Answer [ ]
INJECT 6 One site's contact form held personal data. What changes?
Answer [ ]
INJECT 7 The usual recovery operator is unreachable. Who replaces them?
Answer [ ]
INJECT 8 At the current pace a site will miss its agreed RTO. Who is told,
by whom, and when?
Answer [ ]
GAPS FOUND
[one line each: gap, owner, due date]
PLAN CHANGES REQUIRED
[section, change, owner]
Next tabletop due [YYYY-MM-DD]
A reproducible portfolio recovery exercise
This is the second asset: a procedure for actually recovering a set of sites in plan order, so that the recovery order, capacity and communication are tested together. It uses the single-site worksheet for each site’s detail and adds the portfolio layer on top. It has not been run by this site; every result field is blank.
Preconditions
- Every site in the exercise has a completed single-site restore drill on record, so this exercise tests the plan rather than discovering basic backup faults.
- A separate target environment, in an account the exercise can use without touching production, with indexing blocked.
- Clients informed in advance if their data will be copied into it, and the copies handled under your normal data-protection terms.
- An observer who is not a participant, to keep time.
Procedure
- Choose the scenario and the sites. Pick one runbook scenario — hosting account loss is the most instructive — and three to five sites from the top of the recovery order.
- Start the clock with activation, not with the restore. The exercise begins when the incident lead is notified, because in a real event that is when the client’s downtime starts.
- Follow the plan as written. Retrieve credentials through the documented route, not from the operator’s memory. Where the plan is wrong, note it and continue with a workaround — do not fix the plan mid-exercise.
- Recover in plan order with the number of operators you would really have. Complete each site’s acceptance checks from the single-site worksheet.
- Send the client communications you would send, to an internal mailbox, at the times the plan says.
- Validate and close. Take a fresh backup of one recovered site, as the plan’s close-down section requires, then destroy the exercise environment and record that you did.
- Write the after-action report within a week, and update the plan.
PORTFOLIO RECOVERY EXERCISE RECORD
Date [YYYY-MM-DD] Scenario [runbook name] Plan version [ref]
Incident lead [name] Operators [names] Observer [name]
Target environment [account / location — never production]
ACTIVATION AND NOTIFICATION
A0 Incident lead notified .................. [HH:MM]
A1 Plan invoked ............................ [HH:MM]
A2 All role holders reached ................ [HH:MM]
A3 Backup storage credentials obtained ..... [HH:MM]
A4 Target environment ready ................ [HH:MM]
RECOVERY (one row per site, in plan order)
Order Site Tier Agreed RTO Started Accepted Elapsed from A0 Met?
1 [ ] [ ] [ ] [HH:MM] [HH:MM] [ ] [Y/N]
2 [ ] [ ] [ ] [HH:MM] [HH:MM] [ ] [Y/N]
3 [ ] [ ] [ ] [HH:MM] [HH:MM] [ ] [Y/N]
Single-site worksheet refs .............. [links]
COMMUNICATION
First client message sent .................. [HH:MM] per plan? [Y/N]
Missed-target warning sent, if needed ...... [HH:MM] before target? [Y/N]
RECONSTITUTION
Fresh backup taken of recovered site ....... [ ]
Recovery declared complete by [name] at .... [HH:MM]
Exercise environment destroyed ............. [ ] by [name] on [YYYY-MM-DD]
FINDINGS
Plan steps that were wrong or missing ...... [ ]
Credentials or access that failed .......... [ ]
Capacity: sites that missed RTO only because of queueing [ ]
OUTCOME
[ ] All agreed RTOs met [ ] Some missed [ ] Exercise abandoned
Commitment worksheets to revisit ........... [sites]
Next exercise due .......................... [YYYY-MM-DD]
Measure elapsed time from A0, not from the start of each restore. The difference between the two is the part of recovery time that single-site drills never see — waiting for people, credentials and your turn in the queue.
Step 7 — When a target is missed
It will happen, first in an exercise and eventually for real. Decide in advance what follows, so it is a procedure rather than an argument.
In an exercise, a miss is the most useful result you can get. For each miss, the after-action report should say which of four things will change:
- The setup — more frequent database backups, a pre-provisioned recovery account, a faster restore path.
- The plan — the order, the activation criteria, a missing credential route.
- The people — a second trained operator, a deputy for a role.
- The commitment — go back to the client with the worksheet and agree a target you can demonstrate.
Until one of those is done and re-tested, the commitment worksheet should show the gap. NIST’s term for this is a plan of action and milestones; the agency version is a dated line in the worksheet’s section 5.
In a real incident, the rules are shorter:
- Tell the client before the target passes, not after. A warning with a revised estimate is a different conversation from an apology.
- Do not trade the forensic copy for speed on a suspected compromise. Recovering fast onto the same weakness is not a recovery.
- Write the timeline as it happens. NIST’s reconstitution phase ends with documenting what was done and what went wrong; an after-action report written from memory a week later loses the useful detail.
- Review the contract terms afterwards, calmly. Whatever the agreement says about missed targets applies; the incident is not the time to renegotiate it.
Where host and plugin features fit
A host’s backup and restore features can make a short RTO achievable, and a host’s status page and support route belong in the plan’s contact list. Neither changes who owns the recovery commitment to your client. When you evaluate a host for this purpose, read the vendor’s own documentation and terms, note the date, and ask:
- Does the host’s service level, if there is one, cover restoring your sites, or only the availability of its own platform? These are different promises.
- If the hosting account is suspended or inaccessible, can you still reach the host-held backups? If not, they do not count towards this plan’s hosting-loss scenario.
- Can you take a full off-platform copy on demand, without a support ticket?
Host comparisons on this site are documentary and do not claim recovery performance; see the methodology page for what each evidence label means.
When you should not buy anything
Most of this plan is writing and practice. Before spending on tooling:
- If no single-site restore has been drilled, a product will not fix that. Run the drill first.
- If targets have not been agreed with clients, you do not yet know what to buy. Complete the commitment worksheets first.
- If the plan has never been read aloud in a tabletop, an hour of discussion will find more gaps than a new backup service.
- If the gap is one person, the fix is training a second one.
Buy when an exercise shows a specific gap that only a product or a different platform closes — a restore path that cannot meet an agreed RTO, say — and re-test after buying.
What this does not cover
- Backup mechanics and single-site restores — in the backup and restore checklist.
- Client incident notices — what to say to a client whose site was compromised is a separate piece of work, and legal wording needs a lawyer.
- Contract drafting. This page tells you what the recovery clauses need to say, not how to word them.
- High-availability architectures such as standby replicas or multi-region failover. For most agency client sites, recovery from backup is the realistic strategy; where it is not, that is an architecture decision.
- Your own agency’s business continuity beyond client sites — payroll, office, your own email.
How this page will change
This page is a method and templates. It contains no recovery time, no exercise outcome and no claim that any arrangement meets any target, because nothing was measured for it. A completed tabletop record and portfolio recovery exercise from a controlled test environment, published with timings, gaps and caveats, would be a different article with a different evidence label. It is planned; it is not claimed here.